BetaActiveSolarBatteryAPSLBNL
400 MW hybrid in Pinal, AZ · In queue since September 2023 · Proposed COD June 2027
400 MW
Capacity
1
Components
Solar
2y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 9m
In Study38%
Queue EntrySep 7, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-06-01
Project Details
State
AZ
County
Pinal
Region
West
Developer
—
Utility
Arizona Public Service
Entity
APS
Point of Interconnection
3 Miles South of the Milligan 230KV Substation
Data Source
LBNL