— Project Summary

Queue ID
APS-Q534
Capacity
60 MW
Technology
Solar+Battery
Status
active
Location
Navajo, AZ
Region
West
Developer
IA Status
Cluster Study

BetaActiveSolarBatteryAPSLBNL

60 MW hybrid in Navajo, AZ · In queue since April 2023 · Proposed COD December 2026

60 MW

Capacity

1

Components

Solar

2y 11m

In Queue

Cluster Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 8m

Impact Study25%
Queue EntryApr 4, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-31

Project Details

State

AZ

County

Navajo

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

Twin Arrows - Sunshine 69 kV Line

Data Source

LBNL

No news available for this project.