BetaActiveSolarBatteryAPSLBNL
60 MW hybrid in Navajo, AZ · In queue since April 2023 · Proposed COD December 2026
60 MW
Capacity
1
Components
Solar
2y 11m
In Queue
Cluster Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 8m
Impact Study25%
Queue EntryApr 4, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-31
Project Details
State
AZ
County
Navajo
Region
West
Developer
—
Utility
Arizona Public Service
Entity
APS
Point of Interconnection
Twin Arrows - Sunshine 69 kV Line
Data Source
LBNL
No news available for this project.