— Project Summary

Queue ID
APS-Q524
Capacity
30 MW
Technology
Solar
Status
active
Location
Coconino, AZ
Region
West
Developer
IA Status
Cluster Study

BetaActiveSolarAPSLBNL

30 MW generation in Coconino, AZ · In queue since March 2023 · Proposed COD April 2026

30 MW

Capacity

1

Components

Solar

3 years

In Queue

Cluster Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 1m

Impact Study25%
Queue EntryMar 31, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-04-15

Project Details

State

AZ

County

Coconino

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

Cataract Creek 69kV

Data Source

LBNL