BetaActiveGasAPSLBNL
350 MW generation in Maricopa, AZ · In queue since March 2023 · Proposed COD April 2028
350 MW
Capacity
1
Components
Gas
3 years
In Queue
IA Executed
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 1m
Construction75%
Queue EntryMar 31, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 24–48 months
Commercial Operation
Proposed COD: 2028-04-01
Project Details
State
AZ
County
Maricopa
Region
West
Developer
—
Utility
Arizona Public Service
Entity
APS
Point of Interconnection
Redhawk 500 kV Switchyard
Data Source
LBNL