— Project Summary

Queue ID
APS-Q497
Capacity
300 MW
Technology
Wind
Status
active
Location
Navajo, AZ
Region
West
Developer
IA Status
Cluster Study

BetaActiveWindAPSLBNL

300 MW generation in Navajo, AZ · In queue since March 2023 · Proposed COD October 2027

300 MW

Capacity

1

Components

Wind

3 years

In Queue

Cluster Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 7m

Impact Study25%
Queue EntryMar 21, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-10-31

Project Details

State

AZ

County

Navajo

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

Cholla-Pinnacle peak 345 kV line

Data Source

LBNL

No news available for this project.