— Project Summary

Queue ID
APS-Q493
Capacity
100 MW
Technology
Solar+Battery
Status
active
Location
Pinal, AZ
Region
West
Developer
IA Status
Cluster Study

BetaActiveSolarBatteryAPSLBNL

100 MW hybrid in Pinal, AZ · In queue since February 2023 · Proposed COD January 2025

100 MW

Capacity

1

Components

Solar

3y 1m

In Queue

Cluster Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

1y 11m

Schedule

15 months past proposed COD

Impact Study25%
Queue EntryFeb 13, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-01-15

Project Details

State

AZ

County

Pinal

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

Milligan Switchyard 69 kV

Data Source

LBNL

No news available for this project.