— Project Summary

Queue ID
APS-Q486
Capacity
400 MW
Technology
Solar+Battery
Status
active
Location
Coconino, AZ
Region
West
Developer
IA Status
Cluster Study

BetaActiveSolarBatteryAPSLBNL

400 MW hybrid in Coconino, AZ · In queue since September 2022 · Proposed COD June 2027

400 MW

Capacity

1

Components

Solar

3y 6m

In Queue

Cluster Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 9m

Impact Study25%
Queue EntrySep 29, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-06-30

Project Details

State

AZ

County

Coconino

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

El Dorado-Moenkopi 500 kV Line

Data Source

LBNL