— Project Summary

Queue ID
APS-Q480
Capacity
400 MW
Technology
Solar
Status
active
Location
Navajo, AZ
Region
West
Developer
IA Status
Cluster Study

BetaActiveSolarAPSLBNL

400 MW generation in Navajo, AZ · In queue since September 2022 · Proposed COD December 2025

400 MW

Capacity

1

Components

Solar

3y 6m

In Queue

Cluster Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 3m

Schedule

4 months past proposed COD

Impact Study25%
Queue EntrySep 28, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-01

Project Details

State

AZ

County

Navajo

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

Four Corners - Moenkopi 500kV Line

Data Source

LBNL

No news available for this project.