— Project Summary

Queue ID
APS-Q479
Capacity
165 MW
Technology
Battery
Status
active
Location
Maricopa, AZ
Region
West
Developer
IA Status
Cluster Study

BetaActiveBatteryAPSLBNL

165 MW storage in Maricopa, AZ · In queue since September 2022 · Proposed COD May 2028

165 MW

Capacity

1

Components

Battery

3y 6m

In Queue

Cluster Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5y 8m

Impact Study25%
Queue EntrySep 27, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-05-31

Project Details

State

AZ

County

Maricopa

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

Perryville 69kV Substation

Data Source

LBNL

No news available for this project.