BetaActiveBatteryAPSLBNL
165 MW storage in Maricopa, AZ · In queue since September 2022 · Proposed COD May 2028
165 MW
Capacity
1
Components
Battery
3y 6m
In Queue
Cluster Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 8m
Impact Study25%
Queue EntrySep 27, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-05-31
Project Details
State
AZ
County
Maricopa
Region
West
Developer
—
Utility
Arizona Public Service
Entity
APS
Point of Interconnection
Perryville 69kV Substation
Data Source
LBNL