BetaActiveSolarBatteryAPSLBNL
300 MW hybrid in Maricopa, AZ · In queue since March 2022 · Proposed COD December 2025
300 MW
Capacity
1
Components
Solar
4 years
In Queue
Cluster Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 9m
Schedule
3 months past proposed COD
Impact Study25%
Queue EntryMar 31, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-31
Project Details
State
AZ
County
Maricopa
Region
West
Developer
—
Utility
Arizona Public Service
Entity
APS
Point of Interconnection
Trilby Wash 230kV
Data Source
LBNL
No news available for this project.