BetaActiveSolarBatteryAPSLBNL
60 MW hybrid in Navajo, AZ · In queue since March 2022 · Proposed COD April 2024
60 MW
Capacity
1
Components
Solar
4 years
In Queue
Cluster Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 1m
Schedule
24 months past proposed COD
Impact Study25%
Queue EntryMar 24, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-04-15
Project Details
State
AZ
County
Navajo
Region
West
Developer
—
Utility
Arizona Public Service
Entity
APS
Point of Interconnection
New (to be constructed) 69kV switchyard South of Hwy 99 and .04 miles East of Hwy 87 Winslow, AZ
Data Source
LBNL
No news available for this project.