— Project Summary

Queue ID
APS-Q444
Capacity
60 MW
Technology
Solar+Battery
Status
active
Location
Navajo, AZ
Region
West
Developer
IA Status
Cluster Study

BetaActiveSolarBatteryAPSLBNL

60 MW hybrid in Navajo, AZ · In queue since March 2022 · Proposed COD April 2024

60 MW

Capacity

1

Components

Solar

4 years

In Queue

Cluster Study

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

2y 1m

Schedule

24 months past proposed COD

Impact Study25%
Queue EntryMar 24, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-04-15

Project Details

State

AZ

County

Navajo

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

New (to be constructed) 69kV switchyard South of Hwy 99 and .04 miles East of Hwy 87 Winslow, AZ

Data Source

LBNL

No news available for this project.