— Project Summary

Queue ID
APS-Q437
Capacity
300 MW
Technology
Solar+Battery
Status
active
Location
Maricopa, AZ
Region
West
Developer
IA Status
Cluster Study

BetaActiveSolarBatteryAPSLBNL

300 MW hybrid in Maricopa, AZ · In queue since September 2021 · Proposed COD May 2021

300 MW

Capacity

1

Components

Solar

4y 6m

In Queue

Cluster Study

IA Status

COD target: 2021

Interconnection Timeline

Total Duration

4y 6m

Schedule

59 months past proposed COD

Impact Study25%
Queue EntrySep 30, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2021-05-24

Project Details

State

AZ

County

Maricopa

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

Delaney 500kV Substation (Q276 POI 500kV)

Data Source

LBNL