— Project Summary

Queue ID
APS-Q424
Capacity
200 MW
Technology
Solar+Battery
Status
active
Location
Navajo, AZ
Region
West
Developer
IA Status
Cluster Study

BetaActiveSolarBatteryAPSLBNL

200 MW hybrid in Navajo, AZ · In queue since September 2021 · Proposed COD December 2025

200 MW

Capacity

1

Components

Solar

4y 6m

In Queue

Cluster Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

4y 3m

Schedule

3 months past proposed COD

Impact Study25%
Queue EntrySep 29, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-31

Project Details

State

AZ

County

Navajo

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

Cholla 500kV

Data Source

LBNL