BetaActiveBatteryAPSLBNL
125 MW storage in Navajo, AZ · In queue since September 2021 · Proposed COD December 2025
125 MW
Capacity
1
Components
Battery
4y 6m
In Queue
Cluster Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
4y 3m
Schedule
3 months past proposed COD
Impact Study25%
Queue EntrySep 29, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-31
Project Details
State
AZ
County
Navajo
Region
West
Developer
—
Utility
Arizona Public Service
Entity
APS
Point of Interconnection
Cholla 500kV
Data Source
LBNL
No news available for this project.