750 MW hybrid in Navajo, AZ · In queue since September 2021 · Proposed COD January 2025
750 MW
Capacity
1
Components
Solar
4y 6m
In Queue
Cluster Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 4m
Schedule
15 months past proposed COD
Impact Study25%
Queue EntrySep 28, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-01-08