— Project Summary

Queue ID
APS-Q401
Capacity
700 MW
Technology
Solar+Battery
Status
active
Location
Coconino, AZ
Region
West
Developer
IA Status
Cluster Study

BetaActiveSolarBatteryAPSLBNL

700 MW hybrid in Coconino, AZ · In queue since September 2021 · Proposed COD December 2026

700 MW

Capacity

1

Components

Solar

4y 6m

In Queue

Cluster Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

5y 3m

Impact Study25%
Queue EntrySep 27, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-31

Project Details

State

AZ

County

Coconino

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

Moenkopi - El Dorado 500 kV line

Data Source

LBNL