— Project Summary

Queue ID
APS-Q392
Capacity
270 MW
Technology
Solar+Battery
Status
active
Location
Pinal, AZ
Region
West
Developer
IA Status
Cluster Study

BetaActiveSolarBatteryAPSLBNL

270 MW hybrid in Pinal, AZ · In queue since March 2021 · Proposed COD September 2024

270 MW

Capacity

1

Components

Solar

5 years

In Queue

Cluster Study

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 6m

Schedule

18 months past proposed COD

Impact Study25%
Queue EntryMar 31, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-09-30

Project Details

State

AZ

County

Pinal

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

Tat Momoli-Saguaro 230kV Line

Data Source

LBNL