— Project Summary

Queue ID
APS-Q388
Capacity
323 MW
Technology
Solar+Battery
Status
active
Location
Pinal, AZ
Region
West
Developer
IA Status
Cluster Study

BetaActiveSolarBatteryAPSLBNL

323 MW hybrid in Pinal, AZ · In queue since March 2021 · Proposed COD January 2025

323 MW

Capacity

1

Components

Solar

5 years

In Queue

Cluster Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 10m

Schedule

15 months past proposed COD

Impact Study25%
Queue EntryMar 31, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-01-12

Project Details

State

AZ

County

Pinal

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

Tat Momoli-Saguaro 230kV Line

Data Source

LBNL

No news available for this project.