BetaActiveSolarBatteryAPSLBNL
400 MW hybrid in Maricopa, AZ · In queue since March 2021 · Proposed COD June 2024
400 MW
Capacity
1
Components
Solar
5 years
In Queue
IA Executed
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 3m
Schedule
22 months past proposed COD
Construction75%
Queue EntryMar 31, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2024-06-01
Project Details
State
AZ
County
Maricopa
Region
West
Developer
—
Utility
Arizona Public Service
Entity
APS
Point of Interconnection
Redhawk 500kV Substation
Data Source
LBNL