— Project Summary

Queue ID
APS-Q357
Capacity
150 MW
Technology
Battery
Status
active
Location
Maricopa, AZ
Region
West
Developer
IA Status
IA Executed

BetaActiveBatteryAPSLBNL

150 MW storage in Maricopa, AZ · In queue since September 2020 · Proposed COD December 2023

150 MW

Capacity

1

Components

Battery

5y 6m

In Queue

IA Executed

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

3y 3m

Schedule

28 months past proposed COD

Construction75%
Queue EntrySep 30, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2023-12-10

Project Details

State

AZ

County

Maricopa

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

Freedom 69kV

Data Source

LBNL