— Project Summary

Queue ID
APS-Q354
Capacity
250 MW
Technology
Solar+Battery
Status
active
Location
Maricopa, AZ
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryAPSLBNL

250 MW hybrid in Maricopa, AZ · In queue since September 2020 · Proposed COD December 2023

250 MW

Capacity

1

Components

Solar

5y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

3y 3m

Schedule

28 months past proposed COD

In Study38%
Queue EntrySep 29, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-12-01

Project Details

State

AZ

County

Maricopa

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

Sun Valley 230kV

Data Source

LBNL

No news available for this project.