BetaActiveSolarBatteryAPSLBNL
300 MW hybrid in Yuma, AZ · In queue since September 2020 · Proposed COD August 2022
300 MW
Capacity
1
Components
Solar
5y 6m
In Queue
Construction
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
1y 11m
Schedule
44 months past proposed COD
In Study38%
Queue EntrySep 28, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-08-01
Project Details
State
AZ
County
Yuma
Region
West
Developer
—
Utility
Arizona Public Service
Entity
APS
Point of Interconnection
Orchard 230kV
Data Source
LBNL
No news available for this project.