— Project Summary

Queue ID
APS-Q348
Capacity
300 MW
Technology
Solar+Battery
Status
active
Location
Coconino, AZ
Region
West
Developer
IA Status
Cluster Study

BetaActiveSolarWindBatteryAPSLBNL

300 MW hybrid in Coconino, AZ · In queue since September 2020 · Proposed COD December 2024

300 MW

Capacity

1

Components

Solar

5y 6m

In Queue

Cluster Study

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

4y 3m

Schedule

16 months past proposed COD

Impact Study25%
Queue EntrySep 22, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-12-01

Project Details

State

AZ

County

Coconino

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

Moenkopi El Dorado 500kV Line

Data Source

LBNL

No news available for this project.