BetaActiveSolarBatteryAPSLBNL
450 MW hybrid in Yavapai, AZ · In queue since March 2020 · Proposed COD October 2027
450 MW
Capacity
1
Components
Solar
6 years
In Queue
Cluster Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
7y 7m
Impact Study25%
Queue EntryMar 27, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-10-31
Project Details
State
AZ
County
Yavapai
Region
West
Developer
—
Utility
Arizona Public Service
Entity
APS
Point of Interconnection
Dugas 500kV Substation
Data Source
LBNL
No news available for this project.