— Project Summary

Queue ID
APS-Q335
Capacity
360 MW
Technology
Solar
Status
active
Location
Yavapai, AZ
Region
West
Developer
IA Status
Cluster Study

BetaActiveSolarAPSLBNL

360 MW generation in Yavapai, AZ · In queue since March 2020 · Proposed COD May 2023

360 MW

Capacity

1

Components

Solar

6 years

In Queue

Cluster Study

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

3y 2m

Schedule

34 months past proposed COD

Impact Study25%
Queue EntryMar 27, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-05-31

Project Details

State

AZ

County

Yavapai

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

Yavapai 500kV Substation

Data Source

LBNL

No news available for this project.