— Project Summary

Queue ID
APS-Q334
Capacity
500 MW
Technology
Solar+Battery
Status
active
Location
Maricopa, AZ
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryAPSLBNL

500 MW hybrid in Maricopa, AZ · In queue since March 2020 · Proposed COD November 2023

500 MW

Capacity

1

Components

Solar

6 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

3y 8m

Schedule

28 months past proposed COD

In Study38%
Queue EntryMar 26, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-11-30

Project Details

State

AZ

County

Maricopa

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

Sun Valley 230kV

Data Source

LBNL

No news available for this project.