— Project Summary

Queue ID
APS-Q332
Capacity
350 MW
Technology
Solar+Battery
Status
active
Location
Maricopa, AZ
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryAPSLBNL

350 MW hybrid in Maricopa, AZ · In queue since March 2020 · Proposed COD January 2024

350 MW

Capacity

1

Components

Solar

6 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 10m

Schedule

27 months past proposed COD

In Study38%
Queue EntryMar 24, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-01-12

Project Details

State

AZ

County

Maricopa

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

Hoodoo Wash 500kV Switchyard (Q225 POI)

Data Source

LBNL

No news available for this project.