— Project Summary

Queue ID
APS-Q315
Capacity
50 MW
Technology
Battery
Status
active
Location
Coconino, AZ
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryAPSLBNL

50 MW storage in Coconino, AZ · In queue since September 2019 · Proposed COD October 2022

50 MW

Capacity

1

Components

Battery

6y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

3y 1m

Schedule

41 months past proposed COD

In Study38%
Queue EntrySep 30, 2019

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-10-31

Project Details

State

AZ

County

Coconino

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

Woody Mountain 69kV

Data Source

LBNL

No news available for this project.