— Project Summary

Queue ID
APS-Q314
Capacity
300 MW
Technology
Battery
Status
active
Location
Maricopa, AZ
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryAPSLBNL

300 MW storage in Maricopa, AZ · In queue since September 2019 · Proposed COD December 2022

300 MW

Capacity

1

Components

Battery

6y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

3y 3m

Schedule

40 months past proposed COD

In Study38%
Queue EntrySep 30, 2019

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-12-16

Project Details

State

AZ

County

Maricopa

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

Scatter Wash 230kV

Data Source

LBNL