BetaActiveBatteryAPSLBNL
90.1 MW storage in Yuma, AZ · In queue since March 2019 · Proposed COD December 2022
90.1 MW
Capacity
1
Components
Battery
7 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
3y 9m
Schedule
39 months past proposed COD
In Study38%
Queue EntryMar 29, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-12-31
Project Details
State
AZ
County
Yuma
Region
West
Developer
—
Utility
Arizona Public Service
Entity
APS
Point of Interconnection
Marine Air Base Substation
Data Source
LBNL
No news available for this project.