— Project Summary

Queue ID
APS-Q295
Capacity
250 MW
Technology
Solar+Battery
Status
active
Location
Pinal, AZ
Region
West
Developer
IA Status
IA Executed

BetaActiveSolarBatteryAPSLBNL

250 MW hybrid in Pinal, AZ · In queue since March 2019 · Proposed COD December 2022

250 MW

Capacity

1

Components

Solar

7 years

In Queue

IA Executed

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

3y 9m

Schedule

40 months past proposed COD

Construction75%
Queue EntryMar 27, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2022-12-01

Project Details

State

AZ

County

Pinal

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

Milligan 230kV Substation

Data Source

LBNL

No news available for this project.