— Project Summary

Queue ID
APS-Q280
Capacity
300 MW
Technology
Battery
Status
active
Location
Maricopa, AZ
Region
West
Developer
IA Status
IA Executed

BetaActiveBatteryAPSLBNL

300 MW storage in Maricopa, AZ · In queue since September 2018 · Proposed COD December 2022

300 MW

Capacity

1

Components

Battery

7y 6m

In Queue

IA Executed

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

4y 3m

Schedule

40 months past proposed COD

Construction75%
Queue EntrySep 27, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2022-12-01

Project Details

State

AZ

County

Maricopa

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

Westwing 230kV Substation

Data Source

LBNL

No news available for this project.