BetaActiveBatteryAPSLBNL
250 MW storage in Maricopa, AZ · In queue since June 2018 · Proposed COD January 2021
250 MW
Capacity
1
Components
Battery
7y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
2y 7m
Schedule
63 months past proposed COD
In Study38%
Queue EntryJun 22, 2018
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-01-23
Project Details
State
AZ
County
Maricopa
Region
West
Developer
—
Utility
Arizona Public Service
Entity
APS
Point of Interconnection
Raceway 230kV Substation
Data Source
LBNL