— Project Summary

Queue ID
APS-Q275
Capacity
1000 MW
Technology
Solar+Battery
Status
active
Location
Navajo, AZ
Region
West
Developer
IA Status
IA Executed

BetaActiveSolarBatteryAPSLBNL

1,000 MW hybrid in Navajo, AZ · In queue since March 2018 · Proposed COD December 2020

1,000 MW

Capacity

1

Components

Solar

8 years

In Queue

IA Executed

IA Status

COD target: 2020

Interconnection Timeline

Total Duration

2y 9m

Schedule

64 months past proposed COD

Construction75%
Queue EntryMar 30, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2020-12-31

Project Details

State

AZ

County

Navajo

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

Cholla 500kV Substation

Data Source

LBNL

No news available for this project.