BetaActiveSolarAPSLBNL
1,000 MW generation in Coconino, AZ · In queue since March 2018 · Proposed COD December 2024
1,000 MW
Capacity
1
Components
Solar
8 years
In Queue
IA Executed
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
6y 9m
Schedule
15 months past proposed COD
Construction75%
Queue EntryMar 30, 2018
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2024-12-31
Project Details
State
AZ
County
Coconino
Region
West
Developer
—
Utility
Arizona Public Service
Entity
APS
Point of Interconnection
Cedar Mountain - Moenkopi 500 kV Line
Data Source
LBNL
No news available for this project.