— Project Summary

Queue ID
APS-Q273
Capacity
477 MW
Technology
Wind
Status
active
Location
Navajo, AZ
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveWindAPSLBNL

477 MW generation in Navajo, AZ · In queue since March 2018 · Proposed COD December 2021

477 MW

Capacity

1

Components

Wind

8 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2021

Interconnection Timeline

Total Duration

3y 9m

Schedule

52 months past proposed COD

In Study38%
Queue EntryMar 30, 2018

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2021-12-21

Project Details

State

AZ

County

Navajo

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

Preacher Canyon -Cholla 345kV

Data Source

LBNL

No news available for this project.