— Project Summary

Queue ID
APS-Q270
Capacity
200 MW
Technology
Solar+Battery
Status
active
Location
Navajo, AZ
Region
West
Developer
IA Status
IA Executed

BetaActiveSolarBatteryAPSLBNL

200 MW hybrid in Navajo, AZ · In queue since March 2018 · Proposed COD December 2021

200 MW

Capacity

1

Components

Solar

8 years

In Queue

IA Executed

IA Status

COD target: 2021

Interconnection Timeline

Total Duration

3y 9m

Schedule

52 months past proposed COD

Construction75%
Queue EntryMar 29, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2021-12-23

Project Details

State

AZ

County

Navajo

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

Cholla 500 kV Substation

Data Source

LBNL

No news available for this project.