BetaActiveBatteryAPSLBNL
75 MW storage in Maricopa, AZ · In queue since March 2018 · Proposed COD December 2020
75 MW
Capacity
1
Components
Battery
8 years
In Queue
Construction
IA Status
COD target: 2020
Interconnection Timeline
Total Duration
2y 9m
Schedule
65 months past proposed COD
In Study38%
Queue EntryMar 29, 2018
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2020-12-01
Project Details
State
AZ
County
Maricopa
Region
West
Developer
—
Utility
Arizona Public Service
Entity
APS
Point of Interconnection
Sarival 69kV Sub
Data Source
LBNL
No news available for this project.