— Project Summary

Queue ID
APS-Q264
Capacity
130 MW
Technology
Solar+Battery
Status
active
Location
Pinal, AZ
Region
West
Developer
IA Status
IA Executed

BetaActiveSolarBatteryAPSLBNL

130 MW hybrid in Pinal, AZ · In queue since September 2017 · Proposed COD December 2021

130 MW

Capacity

1

Components

Solar

8y 6m

In Queue

IA Executed

IA Status

COD target: 2021

Interconnection Timeline

Total Duration

4y 3m

Schedule

52 months past proposed COD

Construction75%
Queue EntrySep 29, 2017

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2021-12-22

Project Details

State

AZ

County

Pinal

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

Milligan Substation 230kV

Data Source

LBNL

No news available for this project.