BetaActiveSolarBatteryAPSLBNL
2,000 MW hybrid in Coconino, AZ · In queue since May 2017 · Proposed COD December 2021
2,000 MW
Capacity
1
Components
Solar
8y 10m
In Queue
IA Executed
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
4y 7m
Schedule
52 months past proposed COD
Construction75%
Queue EntryMay 16, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2021-12-24
Project Details
State
AZ
County
Coconino
Region
West
Developer
—
Utility
Arizona Public Service
Entity
APS
Point of Interconnection
Navajo 500kV Substation
Data Source
LBNL
No news available for this project.