— Project Summary

Queue ID
APS-Q252
Capacity
250 MW
Technology
Solar+Battery
Status
active
Location
Yuma, AZ
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryAPSLBNL

250 MW hybrid in Yuma, AZ · In queue since March 2017 · Proposed COD December 2021

250 MW

Capacity

1

Components

Solar

9 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2021

Interconnection Timeline

Total Duration

4y 9m

Schedule

52 months past proposed COD

In Study38%
Queue EntryMar 29, 2017

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2021-12-31

Project Details

State

AZ

County

Yuma

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

Hoodoo Wash 500kV Substation

Data Source

LBNL

No news available for this project.