BetaActiveSolarBatteryAPSLBNL
300 MW hybrid in Maricopa, AZ · In queue since September 2016 · Proposed COD May 2021
300 MW
Capacity
1
Components
Solar
9y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
4y 8m
Schedule
59 months past proposed COD
In Study38%
Queue EntrySep 30, 2016
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-05-22
Project Details
State
AZ
County
Maricopa
Region
West
Developer
—
Utility
Arizona Public Service
Entity
APS
Point of Interconnection
Delaney 500kV Substation
Data Source
LBNL
No news available for this project.