BetaActiveSolarAPSLBNL
20 MW generation in Yuma, AZ · In queue since September 2016 · Proposed COD September 2021
20 MW
Capacity
1
Components
Solar
9y 6m
In Queue
IA Executed
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
5 years
Schedule
55 months past proposed COD
Construction75%
Queue EntrySep 7, 2016
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2021-09-23
Project Details
State
AZ
County
Yuma
Region
West
Developer
—
Utility
Arizona Public Service
Entity
APS
Point of Interconnection
Hoodoo Wash
Data Source
LBNL