BetaActiveSolarBatteryAPSLBNL
500 MW hybrid in Yuma, AZ · In queue since August 2015 · Proposed COD December 2021
500 MW
Capacity
1
Components
Solar
10y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
6y 4m
Schedule
52 months past proposed COD
In Study38%
Queue EntryAug 17, 2015
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-12-22
Project Details
State
AZ
County
Yuma
Region
West
Developer
—
Utility
Arizona Public Service
Entity
APS
Point of Interconnection
Hoodoo Wash 500kV
Data Source
LBNL
No news available for this project.