— Project Summary

Queue ID
APS-Q227
Capacity
500 MW
Technology
Solar+Battery
Status
active
Location
Yuma, AZ
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryAPSLBNL

500 MW hybrid in Yuma, AZ · In queue since August 2015 · Proposed COD December 2021

500 MW

Capacity

1

Components

Solar

10y 7m

In Queue

In Progress (unknown study)

IA Status

COD target: 2021

Interconnection Timeline

Total Duration

6y 4m

Schedule

52 months past proposed COD

In Study38%
Queue EntryAug 17, 2015

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2021-12-22

Project Details

State

AZ

County

Yuma

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

Hoodoo Wash 500kV

Data Source

LBNL

No news available for this project.