— Project Summary

Queue ID
APS-Q225
Capacity
200 MW
Technology
Solar+Battery
Status
active
Location
Maricopa, AZ
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryAPSLBNL

200 MW hybrid in Maricopa, AZ · In queue since September 2014 · Proposed COD December 2021

200 MW

Capacity

1

Components

Solar

11y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2021

Interconnection Timeline

Total Duration

7y 3m

Schedule

52 months past proposed COD

In Study38%
Queue EntrySep 25, 2014

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2021-12-22

Project Details

State

AZ

County

Maricopa

Region

West

Developer

Utility

Arizona Public Service

Entity

APS

Point of Interconnection

Hoodoo Wash 500kV Substation

Data Source

LBNL

No news available for this project.