BetaActiveWindAECLBNL
97.5 MW generation in Lincoln, OK · In queue since October 2021 · Proposed COD December 2026
97.5 MW
Capacity
1
Components
Wind
4y 5m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
5y 2m
Construction75%
Queue EntryOct 22, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2026-12-01
Project Details
State
OK
County
Lincoln
Region
Southeast
Developer
—
Utility
Associated Electric Cooperative, Incorporated
Entity
AEC
Point of Interconnection
Stroud 138kV
Data Source
LBNL
No news available for this project.