— Project Summary

Queue ID
AEC-GI-95
Capacity
247 MW
Technology
Wind
Status
active
Location
Dade, MO
Region
Southeast
Developer
IA Status
IA Executed

BetaActiveWindAECLBNL

247 MW generation in Dade, MO · In queue since December 2020 · Proposed COD December 2026

247 MW

Capacity

1

Components

Wind

5y 3m

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

6 years

Construction75%
Queue EntryDec 4, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2026-12-30

Project Details

State

MO

County

Dade

Region

Southeast

Developer

Utility

Associated Electric Cooperative, Incorporated

Entity

AEC

Point of Interconnection

Jasper-Morgan 345 kV

Data Source

LBNL

No news available for this project.