BetaActiveSolarAECLBNL
96 MW generation in Carroll, MO · In queue since July 2020 · Proposed COD December 2027
96 MW
Capacity
1
Components
Solar
5y 8m
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
7y 5m
Construction75%
Queue EntryJul 24, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-12-30
Project Details
State
MO
County
Carroll
Region
Southeast
Developer
—
Utility
Associated Electric Cooperative, Incorporated
Entity
AEC
Point of Interconnection
Sedalia 69 kV
Data Source
LBNL
No news available for this project.