— Project Summary

Queue ID
AEC-GI-83
Capacity
1018 MW
Technology
Wind
Status
active
Location
Randolph, MO
Region
Southeast
Developer
IA Status
IA Executed

BetaActiveWindAECLBNL

1,018 MW generation in Randolph, MO · In queue since June 2019 · Proposed COD December 2027

1,018 MW

Capacity

1

Components

Wind

6y 9m

In Queue

IA Executed

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

8y 6m

Construction75%
Queue EntryJun 19, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2027-12-01

Project Details

State

MO

County

Randolph

Region

Southeast

Developer

Utility

Associated Electric Cooperative, Incorporated

Entity

AEC

Point of Interconnection

McCredie 345 kV

Data Source

LBNL

No news available for this project.