BetaActiveGasAECLBNL
52 MW generation in Mayes, OK · In queue since January 2019 · Proposed COD September 2020
52 MW
Capacity
1
Components
Gas
7y 2m
In Queue
IA Executed
IA Status
COD target: 2020
Interconnection Timeline
Total Duration
1y 8m
Schedule
67 months past proposed COD
Construction75%
Queue EntryJan 18, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 24–48 months
Commercial Operation
Proposed COD: 2020-09-28
Project Details
State
OK
County
Mayes
Region
Southeast
Developer
—
Utility
Associated Electric Cooperative, Incorporated
Entity
AEC
Point of Interconnection
Chouteau 161 kV
Data Source
LBNL
No news available for this project.